Scofield
Attempts to Clarify Facts About Lewis Center
To
the Editors:
It is impossible to address all the issues raised by Professor Orrs
Nov. 30 letter in the allotted space. A more detailed response is
posted at http://www.oberlin.edu/~physics/Scofield/Essays/LongResponse.htm.
Here I address a few of the issues raised.
Professor Orr says that, During the prime months from March
through October, sunlight provided 62 percent of total building
energy use. This information is about as useful as a stockbroker
telling you that Enron stock increased in value for 300 of the last
365 days. If you spent $450,000 to install a PV array on the Cox
Administration building you would achieve similar results. Dominant
energy consumption for buildings in our climate occurs during winter
months. For these four months (Nov. 2000 Feb. 2001) the Lewis
Center actually consumed 20 percent more energy than the eight months
mentioned, and during that time its PV array produced roughly 6
percent of the energy consumed.
Professor Orr suggests that there are just one or two correctable
engineering flaws. History suggests that Orr, whose degree is in
International Relations, does not have an adequate understanding
of the buildings mechanical design. The flaws are numerous
and not easily solved. The building contains not one but two 112kW
electric boilers, two electric air heaters (10kW and 16kW), and
an electric hot water heater. All 23 of its heat pumps are inappropriate
for a geothermal heating system and will likely need to be replaced.
(In that event they will join 21 other heat pumps that waste away
in College storage from an earlier design mistake.) Roughly 50 percent
of the buildings supply air escapes without energy recovery
and the building HVAC system is, by design, unable to save energy
when users open windows or a sensor indicates a room is unoccupied.
The list goes on. The College has only begun to address the first
of these problems.
Professor Orr says that steam from a coal-fired boiler was inconsistent
with the goal to rely exclusively on renewable energy. He further
suggests that a fuel cell is consistent with this goal. The first
assertion raises troubling questions about the project history,
while the second is simply incorrect see the longer essay.
With regard to energy used by the living machine of course
it should be included in the buildings energy consumption.
To do otherwise, while counting its square footage and claiming
that the building processes its own waste, is intellectually dishonest.
And to claim that the excessive energy use is associated with un-anticipated
building use is simply disingenuous. To lower their projected energy
use the design team adopted a contracted building schedule. (What
a novel idea save energy by not using the building!) But
their true expectation was disclosed by architect Kevin Burke in
the Apr/May 2000 Environmental Design and Construction magazine.
Its a popular building, and will most likely be used
seven days a week, he said. We even envision weddings
there in the future.
Professor Orr suggests that a reporter misread his slide
plausible, but inconsistent with the facts. A video tape shows that
Orr misread his own slide saying. This is the past three months,
and I could add a bar here for the fourth month. The light blue
here is what we exported, and what we exported back to the grid
is about 25 percent more than we used. Orrs data shows
that the PV-Array produced just 4 percent (not 25 percent) more
energy than the building consumed. If transformer losses are included
the result flips, with consumption exceeding production by 6 percent.
I can affirm many of the goals for this building and many of the
ideas it represents. But the actual building is hardly a new benchmark
for educational architecture! Much can be learned from this building
project things to be emulated and things to be avoided.
Many readers may conclude that I am against sustainable development
and/or have a grudge against Professor Orr. Neither is the case.
Nor am I primarily concerned with this buildings poor mechanical
design with sufficient time and money many of the problems
will eventually be addressed. No, my primary concern is with the
hypocrisy and misrepresentation surrounding this building project.
Since fall 1997 this building, its mechanical design, and its potential
energy performance have been misrepresented repeatedly to the public
and the Oberlin community. I believe that many folks will share
these concerns when the facts surrounding this project become known.
John
Scofield
Professor of physics
|