The
Environment and Oberlin: An Update
Page
4
In
1995, President Nancy Dye authorized planning to construct a 10,000-square-foot,
$2.5 million environmental studies center that would be a model
of ecological design for Oberlin College. The architectural firm
of William McDonough and Partners (WM+P) was hired to oversee the
programming stage, then subsequently to design the building and
supervise construction.The 13,600-square- foot facility was completed
in January 2000. Today, the design and construction budget sits
at $6.5 million, and the College has had two full years to use the
Lewis Center and evaluate its energy performance.
In the seven years since its initial approval, much has been written
about the goals and intent of the Lewis Center, but little has been
written about the building as it was actually constructed or its
energy performance. As more details emerge about the facilitys
design, I have grown concerned that the media and other publications
have failed to capture important aspects of the building and its
design history.
On
the outside, the Lewis Center resembles the building that has been
described all along. But a buildings energy consumption is
not simply a function of architectureit is equally dependent
on engineering. The buildings engineering, or mechanical design,
is hidden within. And it is here that the Lewis Centers design
deviated significantly from its original intent and public description.
Throughout
1997 the architect considered and simulated a range of mechanical
design concepts. But these energy simulations, although useful for
guiding the design process, were not constrained by building codes
and other engineering realities that frustrate real
building projects. In April of that year, WM+P settled on a concept
described as a building that would be heated and cooled by geothermal
heat pumps, with a backup connection to the Colleges central
steam plantadded, reluctantly, to satisfy concerns of the
maintenance department.
But
the first set of mechanical drawings does not support this description.
They instead depict a building not with steam backup, but heated
by steam and cooled by water circulated through ground wells. The
design showed tempered-water heat pumps (similar to those used in
motels for distributing heating from a central plant), not ground-source
heat pumps appropriate for a geothermal building. In short, the
heat pumps reduced the efficiency of an otherwise steam-heated system.
The
discrepancy is but a historical footnote because this design proved
too costly, and the heat pumps and ground wells were eliminated
just days before College trustees met in September 1997 to approve
the final building design and its $6.11 million budget. A mechanical
redesign was authorized. What emerged that fall was a building,
without heat pumps, heated with steam from the Colleges coal-fired
steam plant. Construction documents were developed for this design,
and the project went out to bid in June 1998. Meanwhile, the College
spent about $450,000 to extend the campus southern steam loop
to the construction site. (These lines have never been used, nor
has their expense been included in the Lewis Center budget.) Architect
William McDonough, in a July 9, 1998, New York Times article,
said the building was
like a tree, that gives more than
it takes, that makes oxygen and provides a habitat for hundreds
of species
The article appeared as bids were coming
in for a building heated from coal-fired steam supplied by the Colleges
central heating plant.
Just
weeks before the Lewis Centers September 1998 groundbreaking,
this second mechanical design was abandoned and another redesign
initiated. As I understand it, Professor David Orr agreed to raise
additional funds (as high as $250,000) to return to geothermal heat
pumps and wellsthis time without a connection to the campus
steam plant. The building was to use only electric energy so that
it might one day be powered by a rooftop photovoltaic array (which
generates electricity from sunlight) or a fuel cell.
Groundbreaking went forward with neither a construction contract
nor a mechanical design. Though the mechanical design would not
be completed for another five weeks, the architect released a performance
data sheet that summarized the buildings key features. Included
was the projected annual energy consumption: 63,609 kilowatt-hours,
which is roughly 20 percent of the site energy used by a conventional
building and slightly more than the annual energy expected from
a 3,700square-foot photovoltaic array, thought then to be
the largest array the roof could support. In the October 1998 issue
of Atlantic Monthly, architect McDonough wrote that [the
Lewis Center] is designed to make more energy than it needs to operate
and to purify its own wastewater. Thus began an immense publicity
campaign about this building that would be powered by sunlight and
produce more energy than it used.
But
the third mechanical design differed significantly from that described
by the architect. In a September 1998 memo, WM+Ps engineers,
Lev Zetlin Associates, wrote of their plans to go forward with a
tempered-water heat pump system with the circulating water loop
cooled by ground wells and heated with an electric boiler. This
redesign essentially returned to the very first design
of April 1997, replacing heat from steam with electric boilers.
The historical footnote now becomes important. This
redesign would have led to the least efficient heating system possiblea
building heated entirely by electric, resistive heat!
The
details are uncertain, but drawings dated September 18, 1998, showed
pumps now taking heat from the ground to heat two-thirds of the
building. A 112-kilowatt electric boiler would provide heat to the
remaining third, including the atrium and Living Machine, spaces
that account for 50 percent of the buildings heat load. Revised
drawings issued a month later included a second electric boiler,
as well as two electric air heaters, an electric hot water heater,
and nine fans that exhausted air without energy recovery. The electric
resistive heating power was nearly double the combined heating capacity
of all the heat pumps! The potential electrical use was so large
that in December 1998 engineers upsized the building transformer
to 500 kilowatts10 times larger than the photovoltaic array
intended to power the buildingand similar to the transformer
that serves the local Ames department store, a building nearly six
times larger! When the construction contract was finally signed
in November 1998, it was for a mechanical design that differed significantly
from the one described in documents released at the groundbreaking.
Furthermore, it was incapable of achieving the design intent.
Construction
of the Lewis Center was completed in January 2000 (the 4,700-square-foot
photovoltaic array would be installed 11 months later). One month
into occupancy, it was clear that the Lewis Center consumed far
more energy than the architect had projected. In another month,
it was clear that the assumptions used for the energy projections
did not apply to the building that was actually constructed.
Go
To Page 1 | 2
| 3 | 4
|5 of Paradise for Sale
|